Travelers should expect delays on Holcomb Bridge Road at Ga. 400 beginning Monday as Roswell begins adding sidewalks, crosswalks and pedestrian signals. Work will be performed between 9 a.m. – 3 p.m. or at night.
The project will relocate the eastbound MARTA bus stop between Old Dogwood Road and the Ga. 400 southbound on-ramp. It will also reconstruct the median to extend the eastbound left-turn lane onto Ga. 400.
Work is expected to be complete in November. Total project cost is $336,170 and is funded through the MARTA Offset Funds.