Residents are invited to receive learm more about the East Cobb Pipeline project at a meeting 7 p.m. April 28 at Sterling Estates East Cobb, 4220 Lower Roswell Road, Marietta.

A start date hasn’t been set for work on section three of this project, which will begin at Indian Hills Parkway and Cove Drive.

The current estimate is work will start in early summer.

Currently, crews are installing pipe along Terrell Mill Road west of Powers Ferry Road.

Another crew is working at The Exchange, and a third is continuing the tunnel under Interstate 75.

Cobb Department of Transportation staff will repave and reopen a section of Terrell Mill Road soon.

Work on the section of Terrell Mill Road between Delk and Powers Ferry roads is delayed because of other utility conflicts.

Information: 770-514-5301, cobbcommute.org or ccmwa.org.