During his monthly public report on Tuesday, Cobb County Manager David Hankerson said more of the work is moving inside now on SunTrust Park as the cranes have been removed.
With 75 percent complete, $365.5 million has been spent.
There are 1,100 workers on-site at the ballpark and 265 workers on the mixed-use site.
Through July, more than 2,489 million man hours have been expended with no lost-time injuries.
To date, total work contracted is $406 million for the ballpark.
Work to Cobb County companies is $263 million at nearly 65 percent and $75 million for 18.5 percent to Disadvantaged Business Enterprise (DBE) firms with the remainder to other companies.
Interior finish work is well underway with the lower concrete seating bowl completed.
Ongoing is the installation of stadium seats, ramps, elevators, escalators, LED lights on the canopy and exterior sidewalks.