The construction contract for the new public works facility in Stockbridge has been extended more than a month and $57,576.91 in change orders added to the project. Citing rain delays above those allowed in the original contract, 41 days were added and the end date was changed from Oct. 2 to Nov. 30 by vote of the City Council at its Oct. 27 work session.
Four other changes were outlined in the agreement, including a need to regrade a detention pond due to exposure of a sewer line, additional work on a lower parking lot, over-excavation of building footers and rock, and electrical changes as required by Georgia Power. Overall wet conditions were cited as the reason for the latter three items.
About the Author
Keep Reading
The Latest