The Pontiac Silverdome was supposed to implode Sunday morning, but the detonation turned out to be a dud.

Officials with Detroit-based Adamo Group, the demolition company in charge of bringing down the former home of the Detroit Lions and the host of Super Bowl XVI, said the explosion weakened the Silverdome, the Detroit Free Press reported.

The structure could still fall, but the timetable is uncertain.

Rick Cuppetilli, executive vice president with Adamo, said 10 percent of the explosive charges failed to go off due to wiring issues, the Free Press reported.

“Unless we find something in the next few hours researching the wiring, we will take it down mechanically,” Cuppetilli said. “We haven't found the wire yet. It's going to take us a while to research it all.”

Excavators will be used this week to take out the structure unless gravity causes it to fall on its own before then, Cuppetilli said.

So far, there are no plans for a second explosion attempt, the Free Press reported.

About the Author

Keep Reading

Georgia Power's Plant Bowen in Cartersville is shown. The utility wants to add about 10,000 megawatts of power supplies in just five years, mainly to serve data centers. (Hyosyb Shin/AJC 2015)

Credit: Hyosub Shin/AJC

Featured

Fulton County Superior Court Judge Robert McBurney — pictured during a hearing Monday, Dec. 15, 2025 — has cleared the way for Georgia's State Election Board to obtain Fulton ballots and other documents from the 2020 election. (Arvin Temkar/AJC)

Credit: Arvin Temkar/AJC