AN UPDATE ON GEORGIA POWER’S LONG-TERM PLAN:
Georgia’s Public Service Commission approved a long-run plan last July mandating that Georgia Power produce more electricity from solar, wind and other renewable sources than the Atlanta utility originally had proposed.
Georgia Power said it is in the initial stages of getting the PSC’s approval for its first batch of new power-generating capacity from such sources —525 megawatt — under the 2016 plan. It calls for Georgia Power to add 1,600 megawatts of renewable power within six years, mostly through contracts with utility-scale projects built by other companies.
The PSC also approved Georgia Power’s request to spend $99 million — it would be at least $175 million including long-term financing costs — for a preliminary study of a site near Columbus for a potential nuclear power plant.
But the utility recently suspended that study after Tokyo-based Toshiba disclosed that it has lost $6 billion building Georgia Power’s Plant Vogtle nuclear plant near Augusta and another project in South Carolina. Toshiba, which is providing the reactors for those projects, also said it will not be building any new nuclear plants.
Georgia Power’s long-term plan also called for closing one coal-fire unit and two oil-fired units at Plant Mitchell near Albany, and an oil-fired unit at Plant Kraft near Savannah. All of those units, representing a total of 234 megawatts of capacity, had already been shut down and were officially retired when the PSC approved the 2016 long-term plan, according to Georgia Power.
There was only “minimal staffing” at the two plants, Georgia Power said, because most employees at the two plants had been reassigned, retired or left for other jobs.
The Plant Kraft facility is being donated to the Georgia Ports Authority. Georgia Power hasn’t decided what to do with the Plant Mitchell facility.
The 2016 plan also approved a feasibility study for wind power generators on extra tall towers in Georgia. Georgia Power said it has purchased the instruments needed to test wind speed at a height of 600-plus feet, and will study potential locations over the next two years.
THE AJC’S JULY 2016 STORY:
Georgia Power is making a big move into solar power and other renewable energy — about three times bigger than it originally planned — under a deal state regulators are expected to approve today.
If the Public Service Commission’s five-member board approves a recent compromise on Georgia Power’s long-term plan, the utility will add as much as 1,600 megawatts of new renewable energy capacity, or roughly enough “green” capacity to power about 264,000 homes. Most of the increase would be over six years.
“It’s going to be a sizable increase in renewable energy, ” said former PSC commissioner Bobby Baker, who now represents the Southern Alliance for Clean Energy, an environmental group.
Baker said Georgia Power currently has about 1,000 megawatts of solar, wind or other renewable power projects online or under development, representing roughly 5 percent of the utility’s overall capacity.
The proposed additions could boost that share to roughly 12 percent. That comes on top of more than 1,000 megawatts of power expected to come from an expansion of the Vogtle nuclear plant near Augusta by 2020.
The Atlanta utility had originally proposed 525 megawatts of solar, wind and other alternative energy to be added over three years in its so-called Integrated Resources Plan. The plan is a 20-year blueprint for the utility’s power generation projects, conservation programs, power plant retirements and other goals that is reviewed every three years by state regulators.
The PSC’s board is voting today on a recent “stipulation” agreement resolving most of the disputes between the utility, regulators, environmental groups and others over the long-term plan. The PSC’s board could amend some pieces before approving it, but it probably won’t toss the agreement aside.
Whatever the PSC board approves could eventually affect Georgians in many ways.The long-term plan will indirectly affect electricity bills, pollution levels, and whether Georgia Power eventually begins building a second nuclear plant in the state.
Nuclear study
One issue still up in the air is whether the utility commission will approve Georgia Power’s request to approve a study — at a cost at least $175 million — to evaluate a site south of Columbus to potentially build a new nuclear plant.
The state regulator’s staff and environmental groups pressed for the higher green energy target. The state regulator wants more renewable energy partly because solar and wind power projects can now produce cheaper energy than traditional sources such as coal and natural gas-fired plants.
“We’re adding it because it’s cheaper than running existing capacity, ” said Tom Bond, the PSC’s director of utilities. “It’s like if you have two cars and one gets 20 miles to the gallon and the other gets 50. It’s cheaper to drive your car that gets 50 miles per gallon.”
Although the long-term plan doesn’t directly affect customers’ rates, Bond said the lower-cost renewable energy will help keep rates down.
Calls for more
During hearings over several months, the regulators’ experts, environmental groups and others had questioned the utility’s planned pace of new solar-and wind-power additions as a slowdown from previous years.
“We’re adding more (renewable) energy but it’s added over a longer period, ” Georgia Power spokesman Jacob Hawkins said. “We definitely think it’s a good stipulated agreement, ” he said, that will broaden the utility’s sources of power and save money for customers.
There are big differences between the power-generating capacity of traditional and renewable energy power plants. Most nuclear and gas-fired plants run full-time, so 1 megawatt from those plants supplies about 1,000 homes. Most renewable energy plants only produce when the wind blows or the sun shines, so 1 megawatt from those plants supplies homes only part of the day, or in effect significantly fewer homes.
But solar and wind-powered installations also are much cheaper and quicker to build and run. Georgia Power expects contracts to supply 1,050 megawatts of green energy to cost about $2 billion.
The Vogtle nuclear expansion, on the other hand, is over three years behind schedule and $3 billion over budget.
GEORGIA POWER LONG-TERM PLAN
Under a compromise agreement, Georgia Power will shut down some traditional plants, add some "green"energy plants, and make other changes in coming years. Here are some highlights:
Renewable energy: The utility plans to add up to 1,600 megawatts of renewable energy. It would contract with outside firms to supply up to 1,050 megawatts from large-scale solar power and other renewable energy plants by 2021. The balance would come from smaller projects built by Georgia Power or by factories, offices, churches, small businesses and homes. Most is likely to be solar, though the compromise allows up to 300 megawatts from wind power, likely imported from the Great Plains states.
New nuke study: There was no agreement on Georgia Power's request for a study costing at least$175 million of a potential nuclear power plant south of Columbus. That decision was left to the state regulator's board.
Closing plants: The utility will close one coal unit and two oil-fired units at Plant Mitchell near Albany, and an oil-fired unit at Plant Kraft near Savannah.Combined, they account for 375 megawatts. Limit spending on old plants: The utility agreed to limit annual investments to$1 million at Plant McIntosh, near Savannah, and $5 million at Plant Hammond, near Rome.Critics wanted Georgia Power to close the old power plants, which are used only part of the year during peak demand times.
Coal ash pond project: Georgia Power wants to do a 10 megawatt demonstration solar power project on one of its closed coal ash ponds near a traditional power plant, allowing it to reclaim land and take advantage of its existing power lines.