The Milton City Council has approved a resurfacing and reconstruction contract valued at $596,771 for two city streets.

Blount Construction Co. Inc. of Marietta was awarded the Public Works Department contract for the reconstruction and overlay of New Providence Road, from Arnold Mill Road (Ga. 140) to Ranchette Road; and for the resurfacing and patching of Ranchette, from New Providence to Arnold Mill.

Blount had submitted the lowest of four bids for the work, staff said in a report to the council. According to city bid documents, work is to begin within 10 days of the notice to proceed and be completed by Dec. 31.

About the Author

Featured

Waymo autonomous vehicles operate across 65 square miles inside I-285 and have been involved in six incidents with Atlanta Public School buses since May. Waymo issued a recall because of their cars briefly stopping or slowing down before continuing forward while a bus was stopped and flashing its lights. (Courtesy of Atlanta Public Schools)