The East Cobb Pipeline of the Cobb County-Marietta Water Authority is expected to be completed in late fall. Crews have finished almost all of the pipeline installation within the roadway, according to Cobb District 2 Commissioner Bob Ott.

Currently, crews are working to complete the final tie-ins near the Sope Creek bridge on Lower Roswell Road.

Until final completion of the project in late fall, activities will include final tie-ins at Sope Creek, cleanup, final restoration of properties, paving and the pipeline’s testing and commissioning.

Ott’s weekly newsletter: CobbCounty.org/Ott.

Project hotline: 770-514-5301.

About the Author

Featured

Atlanta Mayor Andre Dickens (right) tours the Vine City neighborhood with his senior advisor Courtney English (left). (Matt Reynolds/AJC 2024)

Credit: Matt Reynolds