The construction contract for the new public works facility in Stockbridge has been extended more than a month and $57,576.91 in change orders added to the project. Citing rain delays above those allowed in the original contract, 41 days were added and the end date was changed from Oct. 2 to Nov. 30 by vote of the City Council at its Oct. 27 work session.

Four other changes were outlined in the agreement, including a need to regrade a detention pond due to exposure of a sewer line, additional work on a lower parking lot, over-excavation of building footers and rock, and electrical changes as required by Georgia Power. Overall wet conditions were cited as the reason for the latter three items.

About the Author

Keep Reading

A person braves 20-degree temperatures on a walk by the Georgia State University campus in Atlanta on Nov. 11, 2025. Another Arctic blast is on the way next week. (Miguel Martinez / AJC)

Credit: Miguel Martinez-Jimenez

Featured

A MARTA operator is seen inside the control room of one of the new MARTA trains during the unveiling of these trains on Thursday, Jan. 30, 2025. (Miguel Martinez/AJC)

Credit: Miguel Martinez-Jimenez