The Atlanta Braves and construction manager American Builders 2017 have agreed upon a Guaranteed Maximum Price of $450 million to build SunTrust Park.

The so-called GMP is not the entire project cost. Rather, it just incorporates the hard construction costs — things like concrete, steel, labor, plumbing and electrical. It does not include soft costs, or things such as fees for attorneys, architects or the construction manager.

The stadium has a $622 million budget, although it allows for the Braves to increase it by $50 million at the teams’ discretion. Braves officials have said that may be necessary to provide more parking.

The GMP is security for the team. Any costs above the GMP are covered by the construction manager, unless they result from changes to the stadium requested by the team or the county. In that case, the party requesting the change would have to cover the incremental cost.

About the Author

Keep Reading

U.S. President Donald Trump, center, attends the Gaza International Peace Summit in Sharm el-Sheikh, Egypt with, from left, Paraguay's President Santiago Pena, Indonesian President Prabowo Subianto, Cyprus' President Nikos Christodoulides and Hungary's Prime Minister Viktor Orban, Monday, Oct. 13, 2025. (Suzanne Plunkett/AP)

Credit: AP

Featured

Mathew Palmer, a former Delta Air Lines employee, at his home in Atlanta on Thursday, Oct. 9, 2025.  Palmer was fired less than two weeks after writing a post on social media about the assassination of conservative activist Charlie Kirk. (Natrice Miller/AJC)