The Atlanta Braves and construction manager American Builders 2017 have agreed upon a Guaranteed Maximum Price of $450 million to build SunTrust Park.

The so-called GMP is not the entire project cost. Rather, it just incorporates the hard construction costs — things like concrete, steel, labor, plumbing and electrical. It does not include soft costs, or things such as fees for attorneys, architects or the construction manager.

The stadium has a $622 million budget, although it allows for the Braves to increase it by $50 million at the teams’ discretion. Braves officials have said that may be necessary to provide more parking.

The GMP is security for the team. Any costs above the GMP are covered by the construction manager, unless they result from changes to the stadium requested by the team or the county. In that case, the party requesting the change would have to cover the incremental cost.

About the Author

Keep Reading

Former Fulton County election worker Ruby Freeman talks to her daughter, Wandrea ArShaye "Shaye" Moss, a former Georgia election worker, after she testified before the U.S. House Select Committee at its fourth hearing on its Jan. 6 investigation on Capitol Hill in Washington, D.C., on Tuesday, June 21, 2022. (Yuri Gripas/Abaca Press/TNS)

Credit: TNS

Featured

Former Fulton County election worker Ruby Freeman talks to her daughter, Wandrea ArShaye "Shaye" Moss, a former Georgia election worker, after she testified before the U.S. House Select Committee at its fourth hearing on its Jan. 6 investigation on Capitol Hill in Washington, D.C., on Tuesday, June 21, 2022. (Yuri Gripas/Abaca Press/TNS)

Credit: TNS