The Atlanta Braves and construction manager American Builders 2017 have agreed upon a Guaranteed Maximum Price of $450 million to build SunTrust Park.

The so-called GMP is not the entire project cost. Rather, it just incorporates the hard construction costs — things like concrete, steel, labor, plumbing and electrical. It does not include soft costs, or things such as fees for attorneys, architects or the construction manager.

The stadium has a $622 million budget, although it allows for the Braves to increase it by $50 million at the teams’ discretion. Braves officials have said that may be necessary to provide more parking.

The GMP is security for the team. Any costs above the GMP are covered by the construction manager, unless they result from changes to the stadium requested by the team or the county. In that case, the party requesting the change would have to cover the incremental cost.

About the Author

Keep Reading

State Sen. Jason Anavitarte, R—Dallas, speaks about a bill to ban the TikTok app on all state-owned devices on Thursday, February 16, 2023. (Natrice Miller/AJC)

Credit: Natrice Miller/AJC

Featured

Ceudy Gutierrez reads a book to her 2-year-old son, Matias, at their home in Buford, GA, on Tuesday, Nov. 18, 2025. Ceudy Gutierrez is struggling to make ends meet for herself and her three young kids following her husband’s ICE arrest earlier this fall. (Miguel Martinez/ AJC)

Credit: Miguel Martinez-Jimenez